Infrastructure Guidelines (IGs) Review and Submission Schedule

Submission Deadline and Committee and Board Meeting Schedule

Submission Deadline and Committee and Board Meeting Schedule

The submission deadline for consideration at CPC/Board is typically the date of the Board meeting in the preceding month as outlined below.  The Capital Programme Committee meets in the week preceding the board.

Submission deadline and Board Meeting schedule 20251

Deadline for submission of IG deliverables
for consideration at CPC/Board in the next month
Board Meeting
Monday 9 December 2024 Friday 17 January 2025
Friday 17 January 2025 Friday 21 February 2025
Friday 21 February 2025 Friday 21 March 2025
Friday 21 March 2025 Thursday 24 April 2025
Friday 18 April 20252 Friday 16 May 2025
Friday 16 May 2025 Friday 27 June 2025
Friday 27 June 2025 Friday 25 July 2025
Friday 15 August 2025 Friday 19 September 2025
Friday 19 September 2025 Friday 17 October 2025
Friday 17 October 2025 Friday 21 November 2025
Friday 21 November 2025 Friday 19 December 2025


1
All dates are subject to change.

2 The submission deadline for May Board is 4 weeks in advance of the board meeting, this is to allow sufficient time to review deliverables.

The material to be submitted

The material to be submitted for review is as follows:

  • Final version of the relevant IGs deliverable seeking Approval Gate Approval
    • Preliminary Business Case [PBC];
    • Detailed Business Case, Project Execution Plan and Procurement Strategy [DBCPEPPS]; or
    • Final Business Case [FBC].
  • Final version of the documents which TAF also requires submission to the Approving Authority.
    • Prior to PBC: Project/Programme Outline Document [POD] (only for schemes with estimated capital costs over €20m)
    • Between the submissions of the POD and PBC: Longlist Assessment Report [LAR] (only for schemes with estimated total costs over €200m).
  • Please bear in mind that the review will be conducted only on final versions, and not on Drafts. All legible intended appendices should also be submitted accompanying the full report.
  • An executive summary report is required if the full document is greater than 10 pages. As a general guideline, the executive summary report should be no more than 10% in length of the full document.