The National Transport Authority (NTA) is the “Approving Authority” for public transport projects in the metropolitan areas of Dublin, Cork Galway, Limerick and Waterford, as well as urban active travel projects nationwide. Projects funded by the NTA are generally proposed by the NTA’s partner organisations known as Sponsoring Agencies. To fulfil our statutory duty to secure the provision of public transport infrastructure on a value for money basis, the NTA requires that Sponsoring Agencies follow these Guidelines with respect to cost estimation, cost profiling, cost reporting and the general management of costs.
Sponsoring Agencies are required to follow these CMG’s in implementing these processes, ensuring that the NTA is informed on all cost related issues and that at each milestone in the development of a project the NTA is consulted and sufficiently informed about the developing project costs to make informed decisions in relation to the application of exchequer monies.
The NTA Cost Management Guidelines have been designed to assist Sponsoring Agencies with the development of appropriate scheme budgets in line with the requirements of the NTA Project Approval Guidelines (PAG’s Phase 1-7). The Guidelines are broken into three cost bands, Band 1 – €0-€500k, Band 2 – €500k – €10m, and Band 3 – €10m and Above, and have been structured to allow Sponsoring Agencies easily identify processes, primary cost management deliverables and minimum cost reporting requirements.
** originally published on 14th March 2023, Updated on 23rd February 2024
Please see below template appendices relating to these guidelines:
These templates have examples of completed forms and spreadsheets
Download Documents / spreadsheets below
- 022-B123 Cost Management Guidelines Glossary (CMG-Glossary_V1 (Information Only)
- Band 1 – Project Deliverables (€0-0.5 Million) Key Cost Management Deliverables
Spreadsheet documents below
Download Documents / spreadsheets below
- 022_B123_Cost Management Guidelines (CMG)-Glossary_V1 (Information Only)
- Band 2 – (€0.5-€10 Million) Project Deliverables
Download Documents and Spreadsheets
- 001_B123_CC (Band 2-Phase 2) Contingency Calculator
- 008_B23_FR_CMG (Band 2-Phase 2) Financial Reporting template – Pre-Construction Financial Dashboard
- 009_B23_SN (Band 2-Phase 2) Situation Notification Summary
- 010_B23_CL (Band 2-Phase 2) Project Checklist
- 011_B23_OCCE-Band-2-Phase-2 Option Comparison Cost Estimate template
- 012_B23_FWCE-Band-2-Phase-2 Feasibility Working Cost Estimate template
Download Documents and Spreadsheets
Download Documents and Spreadsheets
- 001_B123_CC (Band 2-Phase 5) Contingency Calculator
- 008_B23_FR (Band 2-Phase 5) Financial Report template (Pre-Construction Financial Dashboard)
- 010_B23_CL (Band 2-Phase 5) Project Checklist
- 013_B23_QRA (Band 2-Phase 5) Project Risk Analysis & Register
- 015_B23_CER_CMG- Cost-Estimate-Report (Band 2) Cost Management Guidelines
- 017_B23_PTCE-Band-2-Phase-5 Pre-Tender Cost Estimate
- 018_B23_TPCE-Band-2-Phase-5 Total Project Cost Estimate
Download Documents and Spreadsheets
- 019_B23_FD (Band 2-Phase 6) Construction Phase Financial Dashboard
- 020_B23_FR (Band 2-Phase 6) Construction Phase Financial Report (Rev 1) PDF
- 020_B23_FR (Band 2-Phase 6) Construction Phase Financial Report (Rev 1) Xls
- 021_B23_FAR-Band-2-Phase-6 Final Account Report template
Templates:
- 022_B123_Cost Management Guidelines (CMG)-Glossary_V1 (Information Only)
- Band 3 – (€10 Million+) Project Deliverables
Templates
- 001_B123_CC (Band 3-Phase 3) Contingency Calculator
- 008_B23_FR_CMG (Band 3-Phase 3) Financial Report
- 009_B23_SN (Band 3-Phase 3) Situation Notification Summary
- 010_B23_CL (Band 3-Phase 3) Project Checklist
- 013_B23 (Band 3-Phase 3) Risk Register
- 014_B23_PCE-Band-3-Phase-3 Preliminary Cost Estimate
- 015_B23_CER_CMG-Cost-Estimate-Report
Templates
- 001_B123_CC (Band 3-Phase 5) Contingency Calculator
- 010_B23_CL (Band 3-Phase 5) Project Checklist
- 013_B23_QRA (Band 3-Phase 5) Risk Analysis- Risk Register
- 015_B23_CER_CMG-Cost-Estimate-Report
- 017_B23_PTCE-Band-3-Phase-5 Pre-Tender Cost Estimate
- 018_B23_TPCE-Band-3-Phase-5 Total Project Cost Estimate
These templates have blank forms and spreadsheets.
NTA Cost Management Templates
Download Documents / spreadsheets below
Templates
- 001_B123_CC Contingency Calculator spreadsheet
- 001_B123_CC_CMG-Contingency-Calculator-Part-2_V1 document
- 004_B1_QRA_CMG-QRA_REV 1 Risk Analysis- Risk Register
- 004_B1_QRA_CMG-QRA-Guidance-Part-2_V1 Risk Register – Band 1 Projects Guidance Notes
- 005_B1_PCE-Band-1-Phase-3 Preliminary Cost Estimate
NTA Cost Management Templates
Band 2 (€0.5 to €10m)
Templates
- 001_B123_CC Contingency Calculator spreadsheet
- 001_B123_CC_CMG-Contingency-Calculator-Part-2_V1 document
- 008_B23_FR_CMG Financial Report
- 009_B23_SN Situation Notification Summary
- 010_B23_CL Project Checklist
- 011_B23_OCCE-Band-2-Phase-2_Option Comparison Cost Estimate
- 012_B23_FWCE-Band-2-Phase-2_Feasibility Working Cost Estimate
Templates
- 001_B123_CC Contingency Calculator spreadsheet
- 001_B123_CC_CMG-Contingency-Calculator-Part-2_V1 document
- 010_B23_CL Project Checklist
- 013_B23_QRA_CMG-QRA-Guidance-Part-2_V1 Project Risk Register document
- 013_B23_REV 1 Project Risk Register spreadsheet
- 014_B23_PCE-Band-2-Phase-3_Preliminary Cost Estimate
- 015_B23_CER_CMG-Cost-Estimate-Report
Templates
- 001_B123_CC Contingency Calculator spreadsheet
- 001_B123_CC_CMG-Contingency-Calculator-Part-2_V1 document
- 008_B23_FR_CMG Financial Report – Cost Management Guidelines
- 010_B23_CL Project Checklist
- 013_B23_QRA_CMG-QRA-Guidance-Part-2_V1 Risk Analysis- Risk Register document
- 013_B23_REV 1 Project Risk Register
- 015_B23_CER_CMG-Cost-Estimate-Report
- 017_B23_PTCE-Band-2-Phase-5_Pre-Tender Cost Estimate
- 018_B23_TPCE-Band-2-Phase-5_Total Project Cost Estimate
NTA Cost Management Templates
Band 3 (Exceeding €10m)
Templates
- 001_B123_CC Contingency Calculator spreadsheet
- 001_B123_CC_CMG-Contingency-Calculator-Part-2_V1 document
- 008_B23_FR_CMG Financial Report
- 009_B23_SN Situation Notification Summary
- 010_B23_CL Project Checklist
- 013_B23_QRA_CMG-QRA-Guidance-Part-2_V1 Risk Analysis- Risk Register document
- 013_B23_REV 1 Risk Register
- 014_B23_PCE-Band-3-Phase-3 Preliminary Cost Estimate
- 015_B23_CER_CMG-Cost-Estimate-Report
Templates
- 001_B123_CC Contingency Calculator spreadsheet
- 001_B123_CC_CMG-Contingency-Calculator-Part-2_V1 document
- 010_B23_CL Project Checklist
- 013_B23_REV 1 Project Risk Register
- 015_B23_CER_CMG-Cost-Estimate-Report – Cost Management Guidelines
- 016_B23_UPCE-Band-3-Phase-4 Updated Preliminary Cost Estimate
Templates
- 001_B123_CC Contingency Calculator spreadsheet
- 001_B123_CC_CMG-Contingency-Calculator-Part-2_V1 document
- 010_B23_CL Project Checklist
- 013_B23_REV 1 Project Risk Register
- 015_B23_CER_CMG-Cost-Estimate-Report
- 017_B23_PTCE-Band-3-Phase-5 Pre-Tender Cost Estimate
- 018_B23_TPCE-Band-3-Phase-5 Total Project Cost Estimate
The bulletin intends to provide insights to Consultants in the preparation of their cost estimates to better inform their project estimates in which the NTA is the approving authority.
The bulletin will be updated annually, or earlier if the macroeconomic conditions continue unstable.
The latest version of the bulletin was published in February 2024, replacing the May 2023 bulletin and October 2023 supplementary note. It should be used to provide guidance to Sponsoring Agencies on the treatment of future inflation from February 2024 onwards.
For more information on it, please contact capitalprogrammeoffice@nationaltransport.ie
Main document:
Support documents:
- Inflation Bulletin – User Guide
- 2024 NTA Inflation Full Report
- Cover Note to the NTA Inflation Bulletin February 2024
- Information Note_ Application of Inflation Forecasts for the NTA and TII
Download documents
Schedule of Rates
The NTA has developed a Schedule of Rates (SoR) that can be used by Sponsoring Agencies in the development of cost estimates for projects where the NTA is the Approving Authority. The SoR has been developed to assist Sponsoring Agencies, however Sponsoring Agencies are not obligated to use the information in this Schedule (for example, where they have more reliable data sources, have undertaken market testing or have carried out first principle pricing).